TM 55-4920-432-13&P
4-35. TRANSFORMER
4-35
THIS TASK COVERS: REMOVAL AND INSTALLATION
Initial Set-Up:
Personnel Required:
68F Aircraft Electrician
or
35H TMDE Support Specialist
Tools and Equipment:Tool kit (B2) or Shop Set (B4)
Material/Parts:
Transformer, Heat shrink
(D5), Solder (D8)
Equipment Condition: Power disconnected, control
panel open
1.
REMOVAL:
a.
Remove wires from transformer leads.
b.
Remove four nuts (1), lock washers (2), and flat washers (3) from studs holding transformer (4) to
the base.
c.
Remove transformer (4) from base of tester.
2.
INSTALLATION:
a.
Install transformer (4) on base studs.
b.
Secure transformer (4) to base with flat washers (3), lockwashers (2) and nuts (1) on studs.
c.
Solder two wires to transformer using solder (D8) and cover connections with heat shrink (D5).
Performance check (para. 2-5)
GO TO NEXT PAGE
4-48